DFS - Browns Range Heavy Rare Earth Project
Released
Released
Announcement PDF
ASX Announcement
15 September 2025
Definitive Feasibility Study underscores global strategic value of
Browns Range Heavy Rare Earths Project, demonstrates its
technical and financial viability.
Australian heavy rare earths-focused company Northern Minerals Limited (ASX: NTU) (Northern
Minerals or Company) is pleased to announce the outcomes of a Definitive Feasibility Study (DFS)
for the Company’s 100%-owned Browns Range Heavy Rare Earths Project (Browns Range or
Project), located in the East Kimberley region of Western Australia.
DFS Highlights
Strategic heavy rare earth element (HREE) asset underpinned by Project’s technical and financial
credentials
•
•
•
•
•
•
•
1
The Global shift towards reducing carbon emissions and adopting renewable energy
technologies requires scalable and stable supply of critical minerals such as heavy rare
earth elements.
These HRREs components are used in numerous applications such as clean energy
technologies, advanced defence systems, medical applications, humanoid robotics,
automotive applications and consumer electronics.
China overwhelmingly dominates HREE production, controlling nearly all global output
and refining capacity (~99%), the Browns Range Project is seeking to loosen this global
stranglehold over these critical transition elements.
Ongoing geopolitical landscape has reinforced the strategic nature of HREE projects like
Browns Range and the need for the development of an Australia based supply chain.
Browns Range’s value is underscored by actions by governments around the world to
reduce reliance on single country supply chains through policies such as the Australian
Federal Government’s Critical Minerals Strategy including the introduction of its proposed
critical minerals stockpile, the U.S. Defence Production Act and the EU Critical Raw
Materials Act.
Located in the Tier 1 mining jurisdiction of Western Australia, the DFS outlines the Projects
technical and financial viability and highlights the strategic significance of the Project as
a near-development source of dysprosium and terbium (Dy/Tb), two of the most critical
HREE required for high performance permanent magnets ubiquitous in clean energy
technologies.
The Wolverine HREE deposit contains one of the highest known proportions of Dy/Tb
among rare earth element deposits outside of China with the DFS outlining that the
Project is forecast to produce ~8% of the current global Dy/Tb supply 1.The Project is one of
the most advanced pure-play HREE projects of scale outside of China and the only one in
Australia, with first production targeted from 2028 to meet a forecast global shortfall in
Dy/Tb supply.
CRU REE Special Report 2025
Ground Floor, 40 Kings Park Road West Perth WA 6005
T: +61 (0)8 9481 2344
ABN: 61 119 966 353
Offtake arrangements with Tier 1 partner
•
•
•
The Company has a long-term supply agreement with Iluka Resources (ASX: ILU) (Iluka
Supply Agreement) for a binding contract to supply 30,500 tonnes of Total Rare Earth
Oxides (TREO) contained within a 20-30% xenotime concentrate to Australia’s first fully
integrated rare earths refinery at Eneabba, also in Western Australia.
Strategic product synergy, as the HREE-rich concentrate from Browns Range will enhance
Iluka’s rare earth portfolio, strengthening Australia's critical minerals capabilities
Northern Minerals will contribute to Australia’s efforts to establish a fully domestic value
chain, reducing Western dependency on Chinese processing and setting a benchmark for
secure, sovereign supply chains.
Ore Reserve estimate
•
•
•
•
The Ore Reserve Estimate (ORE) for Browns Range is 5.18 Mt at 0.88% TREO for 45,800 t of
TREO, reported in accordance with the JORC Code 2
Dy/Tb accounts for ~70% of the Browns Range total rare earths basket value 3.
The ORE is based on the outcomes of the DFS and the Mineral Resource estimate update
announced 16 January 2025 4
The ORE is classified as 100% Probable Ore Reserve
Mine Plan
•
•
•
•
The Project mine plan includes open pit mining transitioning to underground mining with
production predominantly via end-on longitudinal sublevel caving.
The Project is expected to include 12 years of mining, supporting an 11-year Life of Mine
(LOM) defined as the period from first to final concentrate production.
Detailed mine plans, including mine design and scheduling, have been developed for two
production scenarios as follows:
o The Production Target mine plan, which underpins the DFS and financial valuation
for the Project, and
o The Ore Reserve mine plan, which supports the Ore Reserve estimate.
The Ore Reserve estimate is a subset of the Production Target estimate.
DFS outlines a technically robust project
•
•
•
•
•
•
2
3
4
A robust and industry proven flowsheet has been developed by extensive bench scale and
pilot plant test work which validated the metallurgical performance of processing feed
from the Wolverine deposit.
The Company constructed, commissioned and operated the Browns Range Pilot Plant
from 2017 to 2021, producing and selling to international markets ~1,000 tonnes of Mixed
Rare Earth Carbonate.
Completion of comprehensive specialist studies support the Project mine plan.
CAPEX/OPEX has been developed in accordance with an AACE Class 2 estimate
Front-end Engineering and Design (FEED) activities have commenced, supporting
progress toward project delivery and development readiness.
The Browns Range project site has an operational camp and airstrip, which will assist in
accelerated commencement of construction.
Joint Ore Reserves Committee (JORC), 2012. Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
Based on average individual REO prices in 2024
ASX Announcement 16 January 2025, “2025 – Wolverine Mineral Resource Estimate”
2
Key Project economics and assumptions
•
•
•
•
•
•
•
•
•
Project economics are based on the Production Target mine plan, which is underpinned
by the Wolverine ORE and Mineral Resource Estimate (MRE) and Browns Range Pilot Plant
(BRPP) stockpiles and, project an initial mine life of ~11 years.
Project forecast pre-production capital is A$592 million including A$77.5 million in
contingency.
Project forecast operating costs are ~A$129M per annum with C1 operating cost of
A$31.25/kg TREO (excluding corporate costs).
Project production plan forecast to produce ~17,500 tpa of xenotime concentrate at ~25%
TREO, containing ~4,350 tpa TREO.
The Project forecast delivers an average annual EBITDA of A$175 million, a pre-tax NPV8 of
A$187 million and a pre-tax ~IRR of 12%, with a seven year payback using Base Case pricing
forecasts by CRU International Limited (CRU)5, achieving a US$107/kg TREO Browns
Range average LOM basket price (the Projects current implied TREO basket price is
US$50.90/kg TREO 6).
The Base Case forecast by independent analysts CRU assumes that magnet REO prices
will increase over the next decade as the market enters a sustained market deficit due to
rising demand and slow supply response outside of China.7
The Divergence Case forecast by independent analysts CRU outlines a potential price
upside scenario for non-China supply to satisfy ex-China demand supported by recent
trade restrictions, geopolitical factors and government policies and regulations focusing
on establishing new supply chains outside of China.
The Divergence Case forecast delivers a Project pre-tax NPV8 of A$705 million and pre-tax
IRR of 21%, with a 5.6-year payback.
The Production Target and forecast financial information derived from the Production
Target referred to in this release are underpinned by Probable Ore Reserves
(approximately 85%) and Inferred Mineral Resources (approximately 15%). There is a low
level of geological confidence associated with Inferred Mineral Resources and there is no
certainty that further exploration work will result in the determination of Indicated Mineral
Resources or that the Production Target or forecast financial information reported will be
realised. The Production Target is based on Mineral Resource and Ore Reserve estimates
which have been prepared by Competent Persons in accordance with the JORC Code 2012.
Sound ESG credentials
•
•
•
•
•
The Project is based on 10+ years of baseline environmental surveys and data collection
It also incorporates 10+ years of cultural heritage surveys and monitoring
The Project has executed Native Title Agreements with the Traditional Owner groups.
Heritage surveys are mostly complete for the Project footprint with all key primary
approvals granted and all secondary approvals in place for construction commencement.
The Company has an approved Australian Industry Participation Plan in place to support
local engagement prioritising the East Kimberley community.
Strong government agencies interest
•
The Company has and continues to receive strong interest from government agencies in
Australia and other countries keen to establish new and sustainable rare earth supply
chains.
CRU REE Special Report 2025
Based on the forecast REO assemblage contained within the Company’s Xenotime concentrate based on Asian Metal Index pricing for separated RE oxides as
at 26 August 2025
7
Please refer Key Risks – Volatility of the Price of Rare Earth Elements in the Browns Range Heavy Rare Earth Definitive Feasibility Study Executive Summary in
Appendix 1
5
6
3
•
Project finance discussions are ongoing with export credit agencies in Australia, the US
and Europe.
Ongoing work programs
•
•
•
The Wolverine deposit remains open at depth, providing opportunity for potential
resource expansion.
The Company is undertaking technical work programs to confirm the viability of
incorporating satellite deposits as blending material in the first 30 months of processing
operations.
The Company is actively engaging in growth and exploration activities, including new data
acquisition, geological interpretation and targeting, and ongoing drilling programs
seeking to define resources for a potential extension to the Project
Commenting on the Browns Range Definitive Feasibility Study, Northern Minerals Managing
Director and CEO Shane Hartwig said:
“The completion of this Definitive Feasibility Study is a major milestone for Northern Minerals and
reaffirms the strategic potential of Browns Range as a globally significant, near-term source of
critical heavy rare earths.”
“The DFS outlines a commercially viable, technically robust project with significant upside
potential, conditional on ongoing work programs and the strong forecast HREE prices being
realised. With the Iluka offtake deal, supportive governments in Australia and overseas and key
approvals received, we are well positioned to move with confidence to the next stage of Browns
Range’s development. “
“Rare earth pricing structures remain opaque given the dominance of Chinese supply and until
recently have yet to factor in the strategic imperative recognised and articulated by governments
in the US and Europe for rare earth supply chains based outside of China. Whilst certain reported
index prices for heavy rare earths like Dysprosium and Terbium remain subdued, leading industry
experts are forecasting a significant supply deficit to emerge by 2028. Browns Range is one of the
most advanced HREE project in the world, ideally positioning Northern Minerals to capitalise on
this forecast supply deficit.”
“The current Browns Range project shape contained within the DFS is based only on the
Wolverine Mineral Resource Estimate. The Company will continue to undertake ongoing
exploration across the broader significant Project tenure to expand the development profile of
the Project.”
“The global push to decarbonise is undeniable and irreversible, reinforcing the strategic value of
projects like Browns Range to supply the raw materials that will enable the energy transition.”
“This DFS lays the foundation for bringing Browns Range into production, with our focus now
shifting to securing the right funding solution to enable construction commencement in line
with our schedule as Northern Minerals sets about delivering long-term, sustained value for our
shareholders.”
-------------
4
Cautionary Statement
The Definitive Feasibility Study referred to in this announcement has been undertaken to
determine the viability of Northern Minerals' Browns Range Heavy Rare Earth Project based solely
on the development of the Wolverine deposit via open pit and underground mining methods
(the Project).
The DFS is a technical and economic assessment of the potential viability of the Project. It is based
on detailed technical, economic and geopolitical assessments to a level that the Company
believes is sufficient to support estimation of Ore Reserves. Northern Minerals has previously
commissioned and released the 2015 Feasibility Study (Previous Study). While geological and
metallurgical observations and data from the Previous Study have been leveraged to inform the
outcomes of the DFS, Northern Minerals considers the Previous Study to be superseded by the
DFS. Cost, pricing and other financial assumptions applied to derive economic outcomes under
the Previous Study are historical and do not apply in the current markets for commodities, or
more-specifically, rare earth products. These assumptions have been revised as reported in the
DFS, and Northern Minerals directs investors to rely solely on these updated assumptions with
respect to any investment decision concerning the Company.
The DFS is based on existing Mineral Resources and the presently reported Probable Ore Reserves
defined within the Project. The Mineral Resources and Ore Reserves underpinning the estimated
life of mine production under the DFS (Production Target) have been prepared by a competent
person or persons and reported in accordance with the JORC 2012 Code. The Production Target
comprises Measured (~2%), Indicated (~84%) and Inferred Mineral Resources (~14%). Investors are
cautioned that there is a low level of geological confidence in Inferred Mineral Resources and
there is no certainty that further drilling will result in the determination of Measured or Indicated
Mineral Resources, or that the Production Target will be realised. Of the Mineral Resources
scheduled for extraction in this Production Target, approximately 85% is classified as Probable
Ore Reserves. The proportion of Inferred Mineral Resources is not a determining factor for viability
of the Project.
The DFS outcomes are based on the range of material assumptions regarding modifying factors
outlined in this announcement. Among these material assumptions are the Company's prospects
of securing further debt and equity funding of at least A$592M. Investors should note that there
is no certainty Northern Minerals will be able to raise the required amount of funding when
needed and that access to such funding may be subject to conditions that may or may not be
within Northern Minerals' control. It is also possible that said funding may only be available on
terms that may be dilutive to or otherwise effect the value of Northern Minerals' shares. It is also
possible that Northern Minerals could pursue other value realisation strategies such as a sale,
partial sale or joint venture of the Project. This could materially reduce Northern Minerals'
proportionate ownership of the Project. While Northern Minerals considers all the material
assumptions to be based on reasonable grounds, there is no certainty that they will prove to be
correct or that the outcomes indicated by the DFS will be achieved.
The DFS further assumes the Iluka Supply Agreement remains on foot to supply up to and beyond
the total contracted quantity of 30,500 t contained TREO. The Iluka Supply Agreement is subject
to conditions precedent required to be satisfied by certain dates, some of which have passed as
at the date of this Announcement, which may entitle the parties to terminate the Iluka Supply
Agreement. Northern Minerals and Iluka are in discussions to facilitate satisfaction of the
conditions outstanding or agree suitable extensions when appropriate to the relevant satisfaction
dates. Neither party has exercised, nor indicated that they will exercise, their termination right as
at the date of this Announcement. There can be no guarantee that outstanding conditions will
be satisfied or a suitable extension to the relevant satisfaction dates will be reached. Please refer
5
Key Risks “Iluka Supply Agreement” in the Brown Range Heavy Rare Earth Definitive Feasibility
Study Executive Summary in Appendix 1.
Northern Minerals has concluded it has a reasonable basis for providing the forward-looking
statements included in this announcement and for holding the expectation that it will be able to
complete the development of the Project.
6
Introduction
Northern Minerals is pleased to announce the completion of a DFS for the commercial-scale
development of the Company’s 100%-owned Browns Range Heavy Rare Earths Project.
Northern Minerals commenced HREE-focused exploration on the Browns Range Dome region in
2010 and to date has focused on targets in WA with mineral resources identified in six deposits
across the Company’s granted mining and exploration leases. The most advanced of these
deposits, Wolverine, forms the basis of the DFS.
Work completed in this DFS builds on previous studies commissioned by the Company, including
in 2015, and lessons learnt from the Browns Range Pilot Plant (BRPP) operations. Northern
Minerals’ project development, exploration and technical services teams, working in conjunction
with specialised independent consultants have developed a bottom-up cost estimate in
accordance with an Association for the Advancement of Cost Engineering (AACE) Class 2
estimate.
Key DFS Work Programs and Assumptions
The DFS confirms the Project’s economic and technical viability for development of a mining and
processing operation to produce a xenotime concentrate rich in dysprosium and terbium (Dy/Tb).
Since the Equity Raising in September 2024 8, the Company has completed a substantial work
program to de-risk the mining and processing component of the Project and deliver revised
project costings built on updated vendor pricing. This included:
•
•
•
•
•
Wolverine Mineral Resource Estimate (MRE) updated to an estimated 7.3 Mt @ 0.96% TREO
for 70,500 t of contained TREO.
Revised mining study based on updated MRE.
Further metallurgical variability test work.
Optimisation of the process plant flow sheet and resultant equipment selection.
Initial due diligence with an Independent technical Expert (ITE) completed.
Key DFS Outputs
A summary of the Project physicals, revenue and operating costs as well as financial outcomes
are shown in Table 1, Table 2 and Table 3. Project physicals and financials are based on the
Production Target mine plan underpinned by the Wolverine MRE and ORE.
Table 1 Project Physicals
Physicals
Units
Value
Ore mined
kt
5,870
Ore processed (including stockpile)
kt
6,120
LOM
years
11
Head grade
% TREO
0.88
Concentrate production
t (dry)
181,000
Average concentrate production (steady state)
tpa
17,500
% TREO
25
Concentrate grade
8
Refer to Equity Raising Presentation – 16 September 2024 available at https://northernminerals.com.au/investors/
7
Average TREO recovery to concentrate
%
84
TREO production
t
45,000
Average TREO production
tpa
4,350
DyTb % in TREO
%
10.7
The information presented in Table 2 and Table 3 is based on two sets of rare earth pricing forecast
published in July 2025 by CRU, a highly regarded independent market analyst:
1.
2.
CRU base case (Base Case)
CRU price divergence scenario (Divergence Case).
The financial outcomes of the Project under the Base Case, are sufficiently robust to support
development of a strategic project of this nature. Significant upside is demonstrated under the
Divergence Case and higher pricing environments.
Table 2 Project Revenue and Operating Costs
Note:
•
•
•
Revenue and operating costs
Units
Base
Case
Divergence
Case
Average TREO basket price (applied to
Iluka Supply Agreement)
US$/kg
TREO
107
138
Dy oxide price (LOM average)
US$/kg
636
820
Tb oxide price (LOM average)
US$/kg
2,761
3,566
Revenue
A$M
3,270
4,270
Average revenue – per annum
A$M
343
450
LOM free cashflow (ungeared, post-tax)
A$M
635
1,335
EBITDA
A$M
1,695
2,690
Average EBITDA – per annum
A$M
175
272
C1 operating costs
A$/kg
TREO
31.25
31.25
All-in Sustaining Costs (AISC)
A$M
2,020
2,119
AISC
A$/kg
TREO
44.70
46.90
Figures are subject to rounding.
Average revenue and EBITDA are calculated as the arithmetic annual averages during steady state production.
DFS financial assessment has assumed that the Iluka Supply Agreement pricing structure remains in place for and after the total contracted
quantity of 30,500 t contained TREO has been delivered to Iluka under the terms of the agreement. It has also been assumed that any annual
production volumes in excess of the 5,500 tpa maximum annual quantity are subject to Iluka exercising its right of first refusal and purchasing the
excess volumes as per the agreement pricing structure.
8
While these two pricing cases differ materially, both are considered credible, reflecting the
inherent uncertainties in today’s rare earth oxide (REO) market environment, particularly in the
medium to heavy rare earth category where the Chinese Government announced a broad
package of export curbs in April 2025 that includes not only mined minerals such as dysprosium
and terbium but also permanent magnets. These curbs impacted global supply chains in Western
automakers and defence contractors and underscored China’s near monopoly on rare earth
mining and processing.
Northern Minerals notes that both pricing cases sit above current market pricing for Dy and Tb
oxides. The Projects current implied TREO basket price is ~US$50.90/kg 9. Rare earth supply is
geographically concentrated and the rare earth pricing structure is opaque due to most sales
negotiated on a contract basis between miners and downstream manufacturers. There is no
commodity exchange for rare earths and Chinese market prices are generally taken as reference
for negotiations. The Asian Metal Index is the primary market price reference index, and its
fluctuations have historically been heavily influenced by Chinese policy decisions rather than
supply-demand fundamentals.
The Company has observed that this index is most susceptible to global government policy
actions rather than free market dynamics. For that reason, the Company does not consider the
current market pricing as necessarily a reliable indicator of the medium to long-term market
fundamentals expected to influence the pricing of concentrate sourced from Browns Range.
In addition, Northern Minerals considers the inclusion of financial outcomes for the Project under
the Divergence Case provides investors with a potential upside case reflecting evolving global
rare earth markets, and the potential positive impact. This is evidenced in the recently announced
public-private partnership between the owner of Mountain Pass rare earth mine, MP Materials
(NYSE: MP) and the U.S Department of Defense, providing a floor price, and supporting the
emergence of a two-price market.
The Company notes the terms of the Iluka Supply Agreement includes an upside price sharing
mechanism based on the average realised price Iluka receives for the rare earth elements
contained within NTU’s xenotime concentrate. These arrangements allow NTU to benefit from
the emerging two-price market.
Table 3 Browns Range Project Financial Outcomes
Financial Metrics
Units
Base Case
Divergence Case
Pre-tax NPV8%, real
A$M
187
705
%
12%
21%
A$M
74
443
Post-tax IRR
%
10%
18%
Payback from first
production (post-tax)
yrs
7.0
5.6
Pre-tax IRR
Post-tax NPV8%, real
Based on the forecast REO assemblage contained with the Company’s Xenotime concentrate at current published Asian Metal Index pricing for separated
oxides as at 26 August 2025
9
9
Project Overview
The Project comprises the development of a heavy rare earth elements (HREE) mining and
mineral processing facility approximately 160 kilometres (km) southeast of Halls Creek, WA. The
Company holds granted tenure over the Project area and the mineral rights to an extensive area
of exploration tenements surrounding the Project, both within WA and across the border in the
Northern Territory.
The Project is located within the Company’s WA tenements on the margins of the Browns Range
Dome, a major geological structure with an outcrop spanning approximately 60 km x 30 km (1,500
km2) across the WA and Northern Territory border.
Figure 1 Browns Range geology and location of deposits
10
Infrastructure
The Browns Range project site has existing non-process infrastructure which was constructed as
part of the BRPP in 2017. The existing infrastructure will be retained and expanded where possible
to minimise project cost, risk, and construction duration, allowing the rapid mobilisation of initial
construction activities to support the commencement of the full-scale Project. The proposed new
and expansion infrastructure is detailed in Table 4.
Table 4 Browns Range proposed infrastructure
Item of Infrastructure
Summary
Access road
•
•
Airstrip
•
•
The existing Mine Access Road is ~50 km long
and will be realigned and upgraded where
required
Access to the Project is along the Duncan and
Gordon Down Roads (approximately 156 km)
from the town of Halls Creek where it joins
the Western Australian State Highway
Existing airstrip will be extended to 2,000 m
to suit aircrafts of 76-seat capacity
Refuelling and terminal facility
Accommodation village
•
Village located ~1.3 km south of the process
plant and ~900m north of the airstrip will be
expanded to 352 en-suite rooms with
associated facilities
Power supply
•
Hybrid diesel-solar power station with a N+1
redundancy
Installed capacity of 28.5 megawatts for a
total power demand of 11 megawatts
Up to 44% renewable energy penetration
(solar)
•
•
Fuel storage
•
•
On-site fuel storage of 1.8 million litres
Allows up to two months of fuel storage on
site
Water supply and treatment
•
•
Water demand of 1.3 gigalitres per annum
Water will be from a borefield and associated
water conveying infrastructure ~13.5 km from
the process plant
Water is of good quality and requires very
little treatment
•
Communications
•
•
No permanent communications
infrastructure is available due to the
remoteness of Project area
Low-orbit satellite technology will provide a
communications link at 900 Mbps to 1 Gbps
A plan of the proposed infrastructure is shown in Figure 2.
11
Figure 2 Browns Range existing and proposed new and expanded infrastructure
12
Government Support
The Project has received recognition and support from various Australian government entities at
the Federal, State, and local levels. In WA, key agencies have provided guidance on permitting,
land access and environmental approvals. Northern Minerals has also engaged with the WA
Government to ensure alignment with the State’s strategic priorities in resources development,
regional employment, and economic diversification. In addition, relevant Commonwealth
agencies have indicated their interest in supporting projects that contribute to critical minerals
supply chains, export capacity, and national energy transition goals.
International government agencies have expressed interest in the Project due to its potential to
contribute to global supply security for critical resources. Northern Minerals has engaged with
export credit agencies, and international investment bodies in response to inbound interest to
explore possible avenues of cooperation. Such engagement includes discussions around
financing support, and participation in broader strategic initiatives between Australia and
international partners. This international interest reflects the expected position of WA as a reliable
and stable supplier of key raw materials to global markets.
Mineral Resource
The Project is underpinned by the Wolverine MRE 10, with supplementary material from the
existing Pilot Plant stockpile MRE 11.
Table 5: Mineral Resource estimate (informing the Ore Reserve) as at 15 January 2025 reported above a
0.15 % TREO cut-off grade.
Deposit
Wolverine
Pilot Plant
Stockpiles
Total
Classification
Tonnage
Mt
TREO
Dy2O3
Y2O3
Tb4O7
HREO
/ TREO
TREO
%
kg/t
kg/t
kg/t
%
t
Measured
0.1
0.91
0.84
5.4
0.12
92
1,000
Indicated
4.9
1.13
1.00
6.72
0.15
91
54,400
Inferred
2.4
0.63
0.54
3.6
0.08
87
15,100
Subtotal
7.3
0.96
0.84
5.66
0.12
90
70,500
Measured
0
0
0
0
0
0
0
Indicated
0.16
0.95
0.83
5.5
0.12
89
1,500
Inferred
0.03
0.26
0.20
1.35
0.03
79
90
Subtotal
0.2
0.82
0.71
4.71
0.1
88
1,600
Measured
0.1
0.91
0.84
5.40
0.12
92
1,000
Indicated
5.1
1.12
0.99
6.68
0.15
91
56,000
Inferred
2.4
0.63
0.54
3.57
0.08
86
15,200
Total
7.5
0.96
0.84
5.64
0.12
90
72,200
Notes:
•
Rounding may have caused computational discrepancies.
•
TREO = Total Rare Earth Oxides – La2O3, CeO2, Pr6O11, Nd2O3, Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Lu2O3, Y2O3.
•
HREO = Heavy Rare Earth Oxides – Total of Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Lu2O3, Y2O3.
•
HREO % = HREO/TREO*100
10
11
ASX Announcement 16 January 2025, “2025 – Wolverine Mineral Resource Estimate”
ASX Announcement 28 September 2018 “Mineral Resource and Ore Reserve Update – Post Trial Mining Operations at June 30 2018”
13
Mining Methodology
Mining at Browns Range will be undertaken by open pit mining using conventional drill/blast and
load/haul, followed by underground mining using standard mobile underground fleets and
decline access with production predominantly via end-on longitudinal sublevel caving. The
selected mining methods are appropriate for the deposit based on orebody geometry